- Entered into discussions for providing assistance during Sunrise Radiology implementation project.
- Created new Project in JCAPS 5.1.3 to process Epic ADT messages to ancillary Picis system
- Created new Connectivity Map for EPIC ADT to Picis and configured with needed components in JCAPS 5.1.3
- Created, validated, and compiled new Java Collaboration Definition for EPIC ADT to Picis in JCAPS 5.1.3
- Created new HL7 TCPIP External System for EPIC ADT to Picis under designated domain in JCAPS 5.1.3
- Created and configured new Deployment Profile for EPIC ADT to Picis in JCAPS 5.1.3
- Performed build and deploy on Deployment Profile for EPIC ADT to Picis in JCAPS 5.1.3
- Created new Project in JCAPS 5.1.3 to process Epic ADT messages to Dexter ancillary system
- Created new Connectivity Map for Epic ADT messages to Dexter and configured with needed components in JCAPS 5.1.3
- Created, validated, and compiled new Java Collaboration Definition for Epic ADT messages to Dexter in JCAPS 5.1.3
- Created new HL7 TCPIP External System for Epic ADT messages to Dexter under designated domain in JCAPS 5.1.3
- Created and configured new Deployment Profile for Epic ADT messages to Dexter in JCAPS 5.1.3
- Performed build and deploy on Deployment Profile for Epic ADT messages to Dexter in JCAPS 5.1.3
- Created new Project in JCAPS 5.1.3 to process ADT messages to ancillary IntelliDesk system
- Created new Connectivity Map for Epic ADT messages to IntelliDesk and configured with needed components in JCAPS 5.1.3
- Created, validated, and compiled new Java Collaboration Definition for Epic ADT messages to IntelliDesk in JCAPS 5.1.3
- Created new HL7 TCPIP External System for Epic ADT messages to IntelliDesk under designated domain in JCAPS 5.1.3
- Created and configured new Deployment Profile for Epic ADT messages to IntelliDesk in JCAPS 5.1.3
- Performed build and deploy on Deployment Profile for Epic ADT messages to IntelliDesk in JCAPS 5.1.3
- Allscripts – Completed build of e*Gate components in production Monday 2/1.
- Allscripts – Attended Pre Go-Live status meeting Tuesday 2/2.
- Allscripts – Completed Go-Live to turn e*Gate components on in production the evening of Wednesday 2/3 and generally monitored the status of message processing the rest of the week and have no major issues occurred. Message traffic was very light.
- Intego Nurse Call – Attended status meeting with the team 2/3 and received good feedback from Intego before, during and after the meeting with regards to message filtering requirements and identified that a VPN tunnel will not be necessary because the Intego server sits inside the client network.
- Intego Nurse Call – Completed changes to the message filtering business rules for this interface. In short, the Intego system is only interested in seeing transactions that affect bed assignments, but is also interested in seeing transactions for Inpatient Pre-Admits. Also, completed unit testing of the interface after completing the message filtering business rule changes.
- Intego Nurse Call – Received IP Address and Port Number information from Intego for their interface server and configured the e*Gate component to point to the IP and Port. Completed connectivity test and also completed testing of one A01 transaction late Friday afternoon that was successfully filed into the Intego application. Also generated a series of test ADT’s in the Meditech system that I have set aside for further testing Monday afternoon with Intego.
- Intego Nurse Call – Worked out a strategy with the team to complete basic message testing, then turn on a live feed from Client ADT to the Intego test system most likely late next week.
- Transolutions – Participated in two integrated testing calls for the client Thursday 2/4 and Friday 2/5. Also supported some additional testing after the two conference calls to address issues identified during the calls. Generally speaking, the testing went extremely well with no issues with the e*Gate components of the interface.