- Preparation for Prod package deployment, review of package and issue resolution.
- Working on getting items through QA for Cert deployment.
- Successful connectivity testing with Central Medicity Practice Location.
- Got Rhapsody access to the folders where billing charge files are located and rhapsody can pull the information.
- Scheduling-Came up with a work around for the lack of an ordering Provider in the Scheduling message.
- Placed some code changes in the EPIC messaging which required editing the definition file and the route logic twice
- Uncovered roadblock where the procedure codes used in the Visit Type for scheduling were not the same codes configuration, these need to be re-mapped
- Got the correct procedure codes into the hands of the order group to remap the ordered procedure codes
- Spent time in test learning the system to assist with testing
- Interface Testing for ADT from EPIC to Siemens RMS.
- Interface Testing for Orders from EPIC to Siemens RMS.
- ORU Results for Muse to Epic.
- Facesheet code redesign for Epic HL7 Adt to QuickChart Facesheet format
- Provided supporting documentation of interfaces.
- Assisted with Rhapsody testing
- EPIC to Rhapsody Mapping and Design requirements identified.
- Radiology Interface Vrad testing scheduled
- Work with Client representative to build referral network in pilot practices and beyond in preparation for iNexx inbox deployment with the referral app.
- Working in the Medicity Nexus application, identifying issues and working with client to resolve these.